Network Rail and its contractor will be carrying out a major package of work around Oxford station. This includes replacing Sheepwash Bridge over Castle Mill Stream to enable it to carry additional railway lines, completing Platform 5 and associated track works, and constructing a new western entrance to the station.
To enable this work to be carried out safely, Roger Dudman Way will need to be closed to vehicles for an anticipated period of 20 months, from early 2027 until summer 2029.
During this period, vehicle access to and from Roger Dudman Way will be via Walton Well Road. We will also strengthen the bridge on this route to ensure it can accommodate emergency vehicles.
Pedestrian and cycle access will be maintained throughout the works. A temporary footbridge and cycle bridge is proposed across Castle Mill Stream between the end of Abbey Road and the nursery site to help maintain local connectivity.
Preparatory works, including surveys, are already underway and we expect to award the main construction contract by the end of the year.
We recognise that these works, particularly the road closure and periods of night-time working, will cause disruption for residents. We are sorry for the inconvenience this may cause and are committed to keeping our neighbours informed throughout the project and working to minimise impacts wherever possible.
We would like to invite you to a public drop-in event where you can find out more about the project, ask questions and discuss any concerns with members of the project team.